*Important* SWAN100 Scheduled Downtime, Dec. 5th and 6th

PrintPrintDownload PDFDownload PDF
Added by Steven Schlewitt (11/11/2020 - 13:27) , last updated by Steven Schlewitt (11/19/2020 - 11:09)

The SWAN100 project to add the Glenside (GSD), Roselle (ROD), and Warrenville (WVD) Public Library Districts is nearing go-live. Existing SWAN libraries should prepare by reviewing the following schedule, and preparing for the database rebuild and system downtime.

 

Downtime and use of Offline, Saturday, Dec. 5th and Sunday Dec. 6th

  • Begins at 7 a.m. on Saturday, Dec. 5th.
  • Concludes sometime Sunday, Dec. 6th when SWAN provides "all clear" SWANcom.
  • After seeing "all clear" message, resume work online.
  • All existing 97 SWAN libraries must use WorkFlows Offline Mode during this period.
  • Offline circulation files will be uploaded automatically when reconnecting online.

*Note: If possible, we recommend processing checkouts and preparing hold materials for curbside pickup on Friday, Dec. 4th while the system remains online. This will help to reduce Offline work on the 5th and 6th.

 

Using Offline

If you’re unfamiliar with WorkFlows Offline mode, SWAN has created several tutorials to walk you through the process. We highly recommend trying Offline mode prior to the rebuild day so that we can answer any questions you may have or provide troubleshooting. The Patron Lookup Tools will also be accessible during the offline period.

 

Impacted Services

Beginning at 7 a.m. on Dec. 5th and throughout the offline period, the following services will be unavailable:

Enterprise Catalog

  • *Intermittent* My Account functions (holds, payments, lists, etc)
  • *Intermittent* Item location and availability

Symphony WorkFlows

  • *Intermittent* External SIP2 & Web Services integrations (including external vendor subscriptions, digital materials access)
  • Internal SIP2 integrations for library self-checkout, AMH, and PC reservation
  • WorkFlows - Offline mode must be used for all checkouts

BLUEcloud Applications

  • BLUEcloud Analytics December 5/6th transactions - harvest will be delayed an extra day
  • BLUEcloud Mobile, MobileCirc, BLUEcloud Circ and Cataloging will be unavailable

 

Go-Live timeline

  • November 23, 2020 - Technical Freeze for new libraries
  • November 30-December 6, 2020 - Loading of catalog/item records into SWAN bibliographic database
  • December 5-6, 2020 - Re-indexing of SWAN catalog (all libraries in offline mode)
  • December 6, 2020 - Patron and circulation data load for new libraries
  • December 7-8, 2020 - Existing 97 SWAN libraries return online, new libraries use Offline mode
  • December 9, 2020 - Go-Live (all libraries online)